Approval of Northwest Connector Phase 3 Sewer Change Order
Body
SUMMARY: One manhole must be adjusted, approximately 204 feet of 18-inch sewer line moved, and one manhole requires replacement to work with the existing sewer system. The fully detailed TDOT change and cost is attached. The lines were installed in accordance with the plans. TDOT has placed the burden of payment on the City. The Director of Engineering and the City Attorney have reviewed plans and contracts and did not find a way to place the cost of the change on another entity. The total cost for the change order is $73,935.26 and utilizes previously bid unit price numbers. The Director of Engineering recommends the approval of the change order with TDOT
BUDGET ACCOUNT:
Recommended Action
NECESSARY COUNCIL ACTION: Approve the change order as presented.