File #: 24-0123    Version: 1 Name: Terminal Building Renovations Change Order
Type: Contract Status: Consent Agenda
File created: 3/29/2024 In control: City Council
On agenda: 4/9/2024 Final action: 4/9/2024
Title: Approval for Terminal Building Renovations Change Order
Sponsors: Engineering Department, Tim Begley
Attachments: 1. CSV-Terminal-Rehab-Change Order #1.pdf

Title

Approval for Terminal Building Renovations Change Order

 

Body

SUMMARY: The attached change order is for replacing the bid flooring with tile, replacing the restroom wall finishes with tile, and adding roof supports under two HVAC units. The City will supply the grout and tile which has been donated by Stone Peak Ceramics. The net change in contract price is $21,500 and an additional 30 days will be added to the contract. Staff recommends the approval of the change order.

 

BUDGET ACCOUNT: 110-52500-930-015

 

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the change order.