File #: 17-0028    Version: 1 Name: Hangar Final Change Order
Type: Contract Status: Passed
File created: 1/11/2017 In control: City Council
On agenda: 2/14/2017 Final action: 2/14/2017
Title: Approval of deduct Change Order #2-Final on corporate hangar sitework
Sponsors: Airport, Engineering Department, City Clerk
Attachments: 1. Freitag Change Order #2

Title

Approval of deduct Change Order #2-Final on corporate hangar sitework

 

Body

SUMMARY:

Change Order #2-Final has been submitted by Freitag Construction Co. to reflect final quantities.  The change order is in the deduct amount of $13,296.50.  The project is complete and final payment has been made.

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION:  Approve final change order #2 with Freitag Construction on corporate hangar.