Legislation Details

File #: 24-0295    Version: 1 Name: Genesis Plaza Phase II - Final Plat
Type: Planning Item Status: Regular Agenda
File created: 8/8/2024 In control: Planning Commission
On agenda: 8/15/2024 Final action: 8/15/2024
Title: Genesis Plaza Phase II - Final Plat
Sponsors: Planning Commission
Attachments: 1. (23-67c2 Lot 3 PH II) Scanned Plat

Title

Genesis Plaza Phase II - Final Plat

 

Body

SUMMARY: The developer is proposing phase two of Genesis Plaza. This phase consists of an additional lot and the dedication of the road right-of-way for the newly constructed Donnelly Place. The new lot is 0.98 acres and will be serviced by water and sewer along the new road. Donnelly Place is approximately 740 feet long with a 50-foot right-of-way. At the time of agenda creation, the road has not been completed.

 

A financial guarantee will be provided to the City at the meeting for the amount needed to complete the road, plus the required additional 10%. The new water lines have been installed and accepted by the City. The sewer has been installed, but has not been tested yet. If the test has not been complete by meeting time, a financial guarantee will be provided to ensure proper testing and completion. Staff will inform the Planning Commission at the meeting the status of the road and sewer.

 

A variance is being requested for the turnaround area at the end of the proposed road, Donnelly Place. The developer is proposing an ingress/egress easement in lieu of the required dedicated right-of-way. City staff recommended the use of the easement to not end up with “extra” right-of-way to maintain in the future.

 

STAFF RECOMMENDATION: Staff recommends approval of the plat and variance, subject to any required items that need to be address, as stated at the meeting.

 

Recommended Action

NECESSARY PLANNING COMMISSION ACTION: Approve the plat and variance. Approve any financial guarantees that may be required