File #: 13-0284    Version: 1 Name: Taxiway Extension CO#2
Type: Contract Status: Passed
File created: 8/28/2013 In control: City Council
On agenda: 9/10/2013 Final action: 9/10/2013
Title: Approval of Taxiway Extension Change Order 2 (no additional cost or time)
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Change Order 2 Taxiway Extension.pdf
Related files: 13-0151, 13-0039, 13-0162, 13-0256
Title
Approval of Taxiway Extension Change Order 2 (no additional cost or time)
 
Body
SUMMARY: The taxiway edge circuit was damaged during excavation and due to not being able to follow the original route of the circuit, it was decided that the best course of action would be to re-route the circuit around the existing hangars. TDOT has also changed policy and requested that the excavated area have sod installed and the seeding mulch be removed. The attached change order includes the above mentioned items and removes unused quantities of completed items.
 There are no additional costs to the project due to this change order and the Director of Engineering recommends the approval of the change order.
 
 
BUDGET ACCOUNT: 110-52500-930-011
 
Recommended Action
NECESSARY COUNCIL ACTION: Approve change order number two for the taxiway extension project.