File #: 26-0387    Version: 1 Name: Miller Avenue Water Line Installation Final Change Order
Type: Contract Status: Regular Agenda
File created: 10/1/2026 In control: Work Session
On agenda: 10/6/2026 Final action:
Title: Discussion regarding approval of Miller Avenue Water Line Installation Final Change Order
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Final Balancing Change Order.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsPlayback
No records to display.

Title

Discussion regarding approval of Miller Avenue Water Line Installation Final Change Order

 

Body

SUMMARY: The final balancing change order is recommended for approval. It is a decrease of $13,360.60 with no additional days. By having multiple items over the estimated amount and multiple items under the estimated amount, this change order zeros out all quantities in the contract.

 

BUDGET ACCOUNT: 413-52390-934-012

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the attached change order.