SUMMARY:

Bids were received on the construction of a 500,000 gallon elevated water storage tank to be located on Plateau Road for the Catoosa area.  The low bid was submitted by Caldwell Tanks, Inc. of Louisville, Kentucky and is recommended for acceptance. 

 

BUDGET ACCOUNT:  450-52140-934-004

 

Recommended Action

NECESSARY COUNCIL ACTION:  Accept bid of Caldwell Tanks, Inc.