File #: 12-0239    Version: 1 Name: Meadow Park Dam Change Order #2
Type: Contract Status: Passed
File created: 7/2/2012 In control: City Council
On agenda: 7/10/2012 Final action: 7/10/2012
Title: Matters relative to Meadow Park Dam Renovation Project Change Order #2
Sponsors: Engineering Department
Indexes: Funds Budgeted
Attachments: 1. Meadow Park Dam Renovation Change Order 2
Related files: 12-0363
Title
Matters relative to Meadow Park Dam Renovation Project Change Order #2
 
Body
SUMMARY: The Meadow Park Dam Renovation Project is almost complete. Change order number two is a reduction in cost based on final quantities for certain items which contains monies back from the boat dock allowance, post tension anchor reductions with all components and the redesign/reduction of components of the two buttresses which Council previously approved. The total reduction in contract price is $194,995.65.
 
 
BUDGET ACCOUNT:  413-52390-934-014
 
Recommended Action
NECESSARY COUNCIL ACTION: Approve the attached Change Order Number 2.