File #: 25-0315    Version: Name: Approval of Meadow Creek Drive Water Line Extension - Mainline Utility Extension
Type: Resolution Status: Consent Agenda
File created: 8/14/2025 In control: City Council
On agenda: 9/9/2025 Final action: 9/9/2025
Title: Approval of Meadow Creek Drive Water Line Extension - Mainline Utility Extension
Attachments: 1. Proposed WL Extension Map_Meadowcreek, 2. Water Line Extension Request_Meadowcreek Rd, 3. Cost Estimate_Meadowcreek_WL

Title

 Approval of Meadow Creek Drive Water Line Extension – Mainline Utility Extension

 

Body

SUMMARY: Three property owners along Meadow Creek Drive, located off Taylor’s Chapel Road, have requested the extension of the existing 2-inch water line to their properties. The extension would be approximately 750 feet long. The estimated cost for the extension is $29,410.70.

 

If approved by City Council, the property owners will be responsible for either paying the City the cost estimate to install the line, or provide a financial guarantee in the amount of the cost estimate, plus 10 percent, for the work to be performed by an approved contractor.

 

The Crossville Regional Planning Commission recommends the approval of the water line extension.

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the waterline extension