File #: 23-0052    Version: 1 Name: Hussey Gay Bell Amendment
Type: Contract Status: Passed
File created: 2/2/2023 In control: City Council
On agenda: 2/14/2023 Final action: 2/14/2023
Title: Approval of contract amendment regarding Hwy 127 North utility relocation contracts
Attachments: 1. 0608 - Engineering Agreement - Wastewater 2023.pdf, 2. 0608 - Engineering Agreement - Water 2023.pdf

Title

Approval of contract amendment regarding Hwy 127 North utility relocation contracts

 

Body

SUMMARY: The City currently has a contract with Hussey Gay Bell for the design and construction administration for the Hwy 127 N utility relocations.

 

The contract currently reads for each task:

Water Design and Construction Contract $302,327.74 plus $$89,276.93 for inspection.

Sewer Design and Construction Contract $58,29.23 plus $61,807.11 for inspection.

 

Hussey Gay Bell is requesting an amendment to allow for a total not to exceed rather than breaking into categories which would allow them some flexibility between the tasks. The total not to exceed amounts would be amended to read amounts not to exceed $391,604.67 for water and $120,101.34 for sewer. No additional funding is requested.

 

 

BUDGET ACCOUNT: 450-52140-934-004

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve amendment