File #: 12-0379    Version: 1 Name: Wastewater collection system
Type: Contract Status: Passed
File created: 10/23/2012 In control: City Council
On agenda: 11/13/2012 Final action: 11/13/2012
Title: Matters relative to wastewater collection system
Sponsors: Waste Water Treatment Plant
Attachments: 1. GRW Collection System Study letter
Title
Matters relative to wastewater collection system
 
Body
SUMMARY:  Request to approve sewer collection system I & I Study Proposal from GRW Engineers.  I & I Study was budgeted FY 2012-13 for $45,000 to complete one third of the system.  The estimated cost from GRW is $42,260 which is under budget.  The results of this study will provide information needed to apply for a $500,000 Community Development Block Grant (CDBG) for 2014 and help prioritize improvement projects in the collection system to minimize risk of sewer system overflow during peak rainfall events and serve additional growth.
 
BUDGET ACCOUNT: 413-41920-930-002
 
Recommended Action
NECESSARY COUNCIL ACTION:  Approve contract.