SUMMARY:
Following approval of the agreement with USGS on the gaging station at Basses Creek, USGS realized that they had transposed the agreement amounts. The amounts were correct in the letter, but not in the agreement. The correct amount should be that the City pays $7,500 and USGS pays $6,087. The cost is $15,000 split by both entities, but USGS is eliminating their normal administration fee, which leaves a net contribution for them of $6,087.
BUDGET ACCOUNT: 413-41990-290
Recommended Action
NECESSARY COUNCIL ACTION: Approve revised agreement.