File #: 12-0302    Version: 1 Name: Cumberland Cove Final Chg Order
Type: Contract Status: Passed
File created: 8/9/2012 In control: City Council
On agenda: 8/14/2012 Final action: 8/14/2012
Title: Approval of deduct Change Order #2 in the amount of $200,236.75 for W & O Construction on Cumberland Cove project
Sponsors: City Clerk, Catoosa Department
Indexes: Not applicable
Attachments: 1. W&O - Change Order 2 - Final
Title
Approval of deduct Change Order #2 in the amount of $200,236.75 for W & O Construction on Cumberland Cove project
 
Body
SUMMARY:
The project in Cumberland Cove and additional areas covered in Change Order #1 is now complete.  The attached change order adjusts the contract to actual quantities used in the project.  These adjustments results in a decrease in the contract of $200,236.75.
 
The final costs for construction, engineering, and other related costs totaled approximately $3,779,638.45.  The City received $3,063,767.50 from the Cumberland Cove POA.  With an estimate of $80,000 in tap fees, the City's final cost should be around $635,870.95 for over 60 miles of water line and pump stations.  This cost is being paid through a low-interest loan from Rural Development.
 
BUDGET ACCOUNT:  Not applicable.
 
Recommended Action
NECESSARY COUNCIL ACTION:  Approve final change order #2 with W & O Construction.