Title
Approval of Downtown Waterline Project Final Change Order with Ironwood Construction
Body
SUMMARY: The final change order is attached. This change order includes 27 hours for the time and materials for several unknowns encountered, such as old service lines, repaired leaks on old infrastructure and unmarked sewer services. The change order also contains the final quantities for all unit priced items.
BUDGET ACCOUNT: Budget amendment required (File 16-0391)
Recommended Action
NECESSARY COUNCIL ACTION: Approve the attached change order.