Approval for Terminal Building Renovations Change Order 2
Body
SUMMARY: The current electrical service to the terminal building is fed from a pole. To feed the power from the new ground transformer, the wire must be pulled out of the conduit and rerouted to the ground transformer. The City will reroute the conduit and the Contractor will be responsible for all wiring.
If the existing wire can be reused, the amount of the change order will be $4,200. If new wire is required, the amount of the change order will be $9,500. The contract time will not change with this change order. The City will initially fund the change order and will request future grant funding to cover a portion of the cost. Staff recommends the approval of the change order.
BUDGET ACCOUNT: 110-52500-930-015
Recommended Action
NECESSARY COUNCIL ACTION: Approve the change order.