File #: 16-0363    Version: 1 Name: I/I Final Change Order
Type: Contract Status: Passed
File created: 8/22/2016 In control: City Council
On agenda: 9/8/2016 Final action: 9/8/2016
Title: Approve of final change Order with Gulf Coast Underground for <$66,011.72>
Sponsors: Waste Water Treatment Plant, City Clerk
Attachments: 1. Gulf Coast Underground Final CO

Title

Approve of final change Order with Gulf Coast Underground for <$66,011.72>

 

Body

SUMMARY:

The contract with Gulf Coast Underground, LLC was terminated at the end of the contract time period, as was contemplated in the original contract.  This project was funded through SRF funds and their funding did not extend past the deadline.  Gulf Coast was able to finish the area they were working in.  The remaining work will be included in future projects.  The final change order is for a deduct amount of $66,011.72.

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION:  Approve Change Order #1-Final with Gulf Coast Underground in the deduct amount of $66,011.72.