SUMMARY:
The contract with Gulf Coast Underground, LLC was terminated at the end of the contract time period, as was contemplated in the original contract. This project was funded through SRF funds and their funding did not extend past the deadline. Gulf Coast was able to finish the area they were working in. The remaining work will be included in future projects. The final change order is for a deduct amount of $66,011.72.
BUDGET ACCOUNT:
Recommended Action
NECESSARY COUNCIL ACTION: Approve Change Order #1-Final with Gulf Coast Underground in the deduct amount of $66,011.72.