Approval of Closeout Change Order-Centennial Park Asphalt Paving, Sealing, and Striping
Body
SUMMARY: A final closeout change order for this project is attached and it includes an additional 8.02 tons of asphalt at an additional cost of $1,604.00 for a total contract price of $105,956.00. The Director of Engineering recommends the approval of the change order.
BUDGET ACCOUNT: 110-44400-930-003, 110-44400-940-019
Recommended Action
NECESSARY COUNCIL ACTION: Approve the attached change order with an increase in contract price of $1,604.00.