File #: 13-0240    Version: 1 Name: W & O Chg Order #3
Type: Contract Status: Consent Agenda
File created: 7/31/2013 In control: City Council
On agenda: 8/13/2013 Final action: 8/13/2013
Title: Approval of Change Order #3 (time extension) with W & O Construction on the sewer collection system improvement project
Sponsors: Engineering Department
Attachments: 1. W & O Change Order #3
Title
Approval of Change Order #3 (time extension) with W & O Construction on the sewer collection system improvement project
 
Body
SUMMARY:  Because of the unanticipated TDOT requirements that required changes in the installation of a portion of the sewer line for the project and the unusually wet weather, an extension of 30 calendar days is requested for approval.  The new completion date will be August 3.  There is no change in the costs.
 
BUDGET ACCOUNT:  Not applicable.
 
Recommended Action
NECESSARY COUNCIL ACTION:  Approve Change Order #3 with W & O Construction.