File #: 26-0013    Version: 1 Name: Miller Avenue Booster Station Change Order 1
Type: Contract Status: Consent Agenda
File created: 12/29/2025 In control: City Council
On agenda: 1/13/2026 Final action: 1/13/2026
Title: Approval of Miller Avenue Booster Station Change Order #1
Sponsors: Engineering Department, Tim Begley
Attachments: 1. 4680 - 24-02 CO#1 Miller Avenue Water Booster Station.pdf
Related files: 24-0086

Title

Approval of Miller Avenue Booster Station Change Order #1

 

Body

SUMMARY: Miller Avenue Booster Station change order includes undercut of unsuitable soils and modifying the driveway to decrease the slope of the driveway. The change order is a $35,519.00 increase in the total contract amount. The unsuitable soils were an unknown and the steepness of the driveway was not realized until it was rough graded.

This project is an ARPA grant project and all available grant funds have not been allocated. The Director of Engineering recommends the approval of the attached change order.  

 

BUDGET ACCOUNT:413-52390-934-012

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the attached change order 1.