Title
Approval of Change Order #1 with Plateau Excavation on the CoLinx project
Body
SUMMARY:
Change Order #1 adjusts the contract time by 30 days due to additional undercut that was encountered. It also provides payment of $23,550 for construction testing and observation costs and 42 hours of hammering previously disturbed oversized materials. The cost is under Schedule II, which will be covered by CoLinx.
BUDGET ACCOUNT: 311-41920-930-003
Recommended Action
NECESSARY COUNCIL ACTION: Approve Change Order #1 with Plateau Excavation for $23,550 and 30 additional days.