File #: 14-0065    Version: 1 Name: Plateau Excavation CO#1
Type: Contract Status: Consent Agenda
File created: 2/5/2014 In control: City Council
On agenda: 2/11/2014 Final action: 2/11/2014
Title: Approval of Change Order #1 with Plateau Excavation on the CoLinx project
Sponsors: City Clerk
Indexes: Funds Budgeted
Attachments: 1. Plateau Excavation Chg #1
Title
Approval of Change Order #1 with Plateau Excavation on the CoLinx project
 
Body
SUMMARY:
Change Order #1 adjusts the contract time by 30 days due to additional undercut that was encountered.  It also provides payment of $23,550 for construction testing and observation costs and 42 hours of hammering previously disturbed oversized materials.  The cost is under Schedule II, which will be covered by CoLinx.
BUDGET ACCOUNT:  311-41920-930-003
 
Recommended Action
NECESSARY COUNCIL ACTION:  Approve Change Order #1 with Plateau Excavation for $23,550 and 30 additional days.