File #: 24-0343    Version: 1 Name: Lantana and Main Traffic Signal Change Order 2
Type: Contract Status: Passed
File created: 9/26/2024 In control: City Council
On agenda: 11/12/2024 Final action: 11/12/2024
Title: Approval of Close Out Change Order for Lantana and Main Traffic Signal Replacement (PIN 125617.00)
Sponsors: Engineering Department, Tim Begley
Attachments: 1. 2024-11-01_Change_Order_02_PIN 125617.00.pdf
Related files: 23-0305

Title

Approval of Close Out Change Order for Lantana and Main Traffic Signal Replacement (PIN 125617.00)

 

Body

SUMMARY: The close out change order 2 for Lantana and Main Traffic Signal Replacement Project is attached. The change order is a deduct in the amount of $29,442.00 and does not contain any additional time. Staff recommends the approval of the change order.

 

 

 

BUDGET ACCOUNT:

 

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the Change order contingent on TDOT’s approval.