Title
Approval of Peavine Road Sewer Force Main Additions Close Out Change Order
Body
SUMMARY: The close out change order for the Peavine Road Sewer Force Main Additions project is attached with a deductive amount of $1,101 with no additional days. This change order zeros out all unused quantities.
Staff recommends the approval of the change order.
BUDGET ACCOUNT: 413-52390-934-016
Recommended Action
NECESSARY COUNCIL ACTION: Approve the attached change order.