Title
Approval of modifications to the City’s Paving Schedule
Body
SUMMARY: The Street Department Superintendent recommends that the paving priorities for Maple Street be traded this fiscal year to the Iris Circle extension as shown on the attached drawing and the paving priorities for Goldenbrook Lane be traded this fiscal year to Myrtle Avenue, from the bridge to the City limits, as shown on the attached drawing. The volume of traffic and the rough driving surface on Myrtle Avenue makes it a higher priority than Goldenbrook Lane. Both of these streets are in Brookhaven Subdivision and the waterline replacement project will be underway shortly and it will be better to wait until it is completed.
BUDGET ACCOUNT:
Recommended Action
NECESSARY COUNCIL ACTION: Approve the changes to the paving list.