File #: 23-0329    Version: 1 Name: Airport Obstruction Removal Project Final Change Order
Type: Contract Status: Passed
File created: 9/27/2023 In control: City Council
On agenda: 10/10/2023 Final action: 10/10/2023
Title: Approval of Airport Obstruction Removal Project Final Change Order
Sponsors: Engineering Department, Tim Begley
Attachments: 1. CSV-Final-Balancing-Change Order.pdf
Related files: 22-0327, 22-0358

Title

Approval of Airport Obstruction Removal Project Final Change Order

 

Body

SUMMARY: The Airport Obstruction Removal project was completed with an additional 21 trees needing trimmed which equated to a project overrun of $15,200. The attached change order details the adjustments.

 

If TDOT Aeronautics will adjust the grants for the overrun, Staff also requests approval of  the change to the grant contracts for the additional grant funds.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the final change order and approve the change to the grant contracts for the additional funding if available.