File #: 26-0390    Version: 1 Name: Spec Building Change Order 2
Type: Contract Status: Regular Agenda
File created: 10/2/2026 In control: Work Session
On agenda: 10/6/2026 Final action:
Title: Discussion regarding approval of Industrial Spec Building Change Order 2
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Spec Building (PO 16174) Change Order 02 Letter of Recommendation.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsPlayback
No records to display.

Title

Discussion regarding approval of Industrial Spec Building Change Order 2

 

Body

SUMMARY: A change order pricing for three rock lined channels, additional monies for inspection, and large rock protection at every downspout location is recommended for approval by the Director of Engineering contingent on the grant funding agency approval.

 

The total amount of the change order is an increase of $90,455.00 and a time extension for an additional 52 days. The rock erosion items are needed to alleviate future maintenance and the inspection is based off of hourly work.

 

All of the original contracted work has been completed with the exception of the vapor barrier and the timers for the fans.

 

BUDGET ACCOUNT: 311-41920-931-003

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the change order in the amount of $90,455.00 and the additional 52 days contingent on the grant funding agency approval.