Title
Discussion and action regarding approval of a change order for the Greenway project
Body
SUMMARY: The greenway contract had a unit price of $71.00 per cubic yard for unsuitable subgrade area. The geotech company required the contractor to remove 276.49 cubic yards of unsuitable soil for a total cost of $19,630.79. This change order only includes the unsuitable soil removal and does not have a time extension.
BUDGET ACCOUNT:
Recommended Action
NECESSARY COUNCIL ACTION: approve change order