Title: Discussion and action regarding approval of a change order for the Greenway project
Attachments: 1. Greenway G701-2017 - Change Order 1..pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsPlayback
No records to display.

Title

Discussion and action regarding approval of a change order for the Greenway project

 

Body

SUMMARY: The greenway contract had a unit price of $71.00 per cubic yard for unsuitable subgrade area. The geotech company required the contractor to remove 276.49 cubic yards of unsuitable soil for a total cost of $19,630.79. This change order only includes the unsuitable soil removal and does not have a time extension.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: approve change order