File #: 13-0292    Version: 1 Name: W & O Change Order #4
Type: Contract Status: Passed
File created: 8/30/2013 In control: City Council
On agenda: 9/10/2013 Final action: 9/10/2013
Title: Approval of change order #4 with W & O Construction (time extension)
Sponsors: City Clerk
Indexes: Not applicable
Attachments: 1. W & O Change Order 4
Title
Approval of change order #4 with W & O Construction (time extension)
 
Body
SUMMARY:
W & O Construction has requested an additional 21 calendar days on the sewer line improvements due to weather related conditions and due to unknown utility locations for the tie-ins.  There is no additional cost associated with the request.
BUDGET ACCOUNT:  413-52390-930-011
 
Recommended Action
NECESSARY COUNCIL ACTION:  Approve change order #4 with W & O Construction.