Title
Discussion regarding approval of Spec Building Change Order 1
Body
SUMMARY: Change Order 1 is recommended with a net increase of $64,753.19 in the contract cost.
The change order includes the following:
1. $10,550.29 for revisions to the concrete foundation which included additional concrete and steel due to the building manufactures design.
2. $10,455.90 for a French drain to drain the ground water seeping into the foundation are of the building.
3. $3,747.00 to sawcut the stem wall under all of the doors for the future tenant.
4. $39,025.00 for special inspection from a third party. This item is included in the grant budget and included the geotechnical testing associated with the footers and floor area of the building and also included concrete testing for the foundation and stem walls.
The Engineer of record recommends the approval of the change order.
BUDGET ACCOUNT:
Recommended Action
NECESSARY COUNCIL ACTION: Approve the change order contingent on the grant agencies approval.