Legislation Details

File #: 26-0210    Version: 1 Name: Spec Building Change Order 1
Type: Contract Status: Regular Agenda
File created: 4/30/2026 In control: Work Session
On agenda: 5/5/2026 Final action:
Title: Discussion regarding approval of Spec Building Change Order 1
Sponsors: Engineering Department, Tim Begley
Attachments: 1. 2026-04-24 Change Order 01 (Crossville 2024 Spec Building) - Signed by Sain.pdf, 2. 2025-04-24 Change Order 01 Letter of Recommendation.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsPlayback
No records to display.

Title

Discussion regarding approval of Spec Building Change Order 1

 

Body

SUMMARY: Change Order 1 is recommended with a net increase of $64,753.19 in the contract cost.

 

The change order includes the following:

1.                     $10,550.29 for revisions to the concrete foundation which included additional concrete and steel due to the building manufactures design.

2.                     $10,455.90 for a French drain to drain the ground water seeping into the foundation are of the building.

3.                     $3,747.00 to sawcut the stem wall under all of the doors for the future tenant.

4.                     $39,025.00 for special inspection from a third party. This item is included in the grant budget and included the geotechnical testing associated with the footers and floor area of the building and also included concrete testing for the foundation and stem walls.

 

The Engineer of record recommends the approval of the change order.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the change order contingent on the grant agencies approval.