File #: 21-0381    Version: 1 Name: CDBG 2020 Sewer Rehab
Type: Contract Status: Passed
File created: 12/1/2021 In control: City Council
On agenda: 12/14/2021 Final action: 12/14/2021
Title: Approval of CDBG 2020 Sewer Rehab Project Change Orders 2 and 3
Sponsors: Engineering Department, Tim Begley
Attachments: 1. CDBG 2020 Change Order 2, 2. Proposed_CO3Final.pdf

Title

Approval of CDBG 2020 Sewer Rehab Project Change Orders 2 and 3

 

Body

SUMMARY: Attached for approval is Change Order #2 with a decrease in contract price of $932.00, which was necessary due to quantities based on the work completed and work remaining.  Also attached for approval is Change Order #3 with a decrease in contract price of $69,508.00, which is the final/close out change order and changes all remaining items to zero.

 

The funding agency will not approve a pay request from the contractor if an item is over the contract amount and these change orders balance a portion of the overruns and underruns on completed items.

 

The Director of Engineering recommends approval of the change orders. 

 

BUDGET ACCOUNT: 413-52390-934-009

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve Change Orders.