Title
Approval of Sewer Rehab Closeout Change Order
Body
SUMMARY: The sewer rehab project is a unit price project. The closeout change order removes or adds money and/or time to the project to bring the remaining monies in the contract to zero and to eliminate a claim for time damages. The closeout change order is attached and shows a net decrease in the contract price of $13,016.86 and an increase in time of 45 days.
The Director of Engineering recommends the approval of the change order.
BUDGET ACCOUNT:
Recommended Action
NECESSARY COUNCIL ACTION: Approve the closeout change order.