File #: 25-0030    Version: 1 Name: Sewer Rehab Closeout Change Order
Type: Contract Status: Consent Agenda
File created: 1/15/2025 In control: City Council
On agenda: 2/11/2025 Final action: 2/11/2025
Title: Approval of Sewer Rehab Closeout Change Order
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Change Order 1_PUCC.pdf
Related files: 23-0352

Title

Approval of Sewer Rehab Closeout Change Order

 

Body

SUMMARY: The sewer rehab project is a unit price project. The closeout change order removes or adds money and/or time to the project to bring the remaining monies in the contract to zero and to eliminate a claim for time damages. The closeout change order is attached and shows a net decrease in the contract price of $13,016.86 and an increase in time of 45 days.

The Director of Engineering recommends the approval of the change order.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the closeout change order.