File #: 12-0363    Version: 1 Name: MPL Final Change Order
Type: Contract Status: Passed
File created: 10/3/2012 In control: City Council
On agenda: 10/9/2012 Final action: 10/9/2012
Title: Matters relative to Meadow Park Dam Final Change Order
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Meadow Park Dam Renovation Project Final Change Order Revised 2.pdf
Related files: 12-0239
Title
Matters relative to Meadow Park Dam Final Change Order
 
Body
SUMMARY: The Meadow Park Dam Renovation Project is complete and other agencies have given their approval. The final closeout change order is attached as "Change Order Number 2 Revised ".This change is a reduction in cost based on final quantities for all items and changes previously approve by the Council. It contains monies back from the boat dock allowance, post tension anchor reductions with all components and the redesign/reduction of components of the two buttresses which Council previously approved. The total reduction in contract price is $661,813.49.
 
 
BUDGET ACCOUNT: 413-52390-934-014
 
 
Recommended Action
NECESSARY COUNCIL ACTION: Approve the attached Closeout Change Order.