Matters relative to Meadow Park Dam Final Change Order
Body
SUMMARY: The Meadow Park Dam Renovation Project is complete and other agencies have given their approval. The final closeout change order is attached as "Change Order Number 2 Revised ".This change is a reduction in cost based on final quantities for all items and changes previously approve by the Council. It contains monies back from the boat dock allowance, post tension anchor reductions with all components and the redesign/reduction of components of the two buttresses which Council previously approved. The total reduction in contract price is $661,813.49.
BUDGET ACCOUNT: 413-52390-934-014
Recommended Action
NECESSARY COUNCIL ACTION: Approve the attached Closeout Change Order.