File #: 15-0049    Version: 1 Name: Airport Tree Removal Project Final Change Order
Type: Contract Status: Passed
File created: 1/27/2015 In control: City Council
On agenda: 2/10/2015 Final action: 2/10/2015
Title: Approval of Airport Tree Removal Project Final Change Order
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Final Change Order
Title
Approval of Airport Tree Removal Project Final Change Order
 
Body
SUMMARY: The final quantities for this project have been tabulated, in the attached change order, as a $5,538.70 reduction in the contract price.
 
BUDGET ACCOUNT:  110-52500-930-009
 
Recommended Action
NECESSARY COUNCIL ACTION: Approve change order in the deduct amount of $5,538.70 with Norris Brothers Construction.