File #: 19-0053    Version: 1 Name: Airfield Pavement Rehabilitation
Type: Resolution Status: Passed
File created: 2/12/2019 In control: Call for Special Meeting
On agenda: 2/14/2019 Final action: 2/14/2019
Title: Discussion and action on NAICO Settlement for Airfield Pavement Rehabilitation
Attachments: 1. NAICO Settlement Agreement

Title

Discussion and action on NAICO Settlement for Airfield Pavement Rehabilitation

 

Body

SUMMARY:  The National American Insurance Company (performance bonding company for Cantrell Construction) has proposed the attached “Settlement Agreement” which includes payment for damages in the amount of $76,984.07 and no payments to Cantrell Construction. 

 

City staff has calculated the City’s damages at $76,984.07 as detailed below:

Cantrell’s Original Bid                       $608,130.00

Axtells’ Rebid                                    $661,452.50

Atkins’ additional engineering fees  -$20,637.00

Total Contracted Damages              -$ 73,959.50

 

Additional Work Performed by the City:

Removal of flowable fill and replace with Concrete -$2,334.30

Temporary 4 inch taxi line -$690.27

 

Total Damages = $76,984.07

 

BUDGET ACCOUNT:110-33477

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve settlement agreement