File #: 13-0338    Version: 1 Name: Satsuma Drive Abutment Project Closeout
Type: Contract Status: Consent Agenda
File created: 10/1/2013 In control: City Council
On agenda: 10/8/2013 Final action: 10/8/2013
Title: Approval of Satsuma Drive Abutment Project final change order in the deduct amount of $2,957.20
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Change Order No 1 - Final Adjustments (2).pdf
Related files: 12-0512
Title
Approval of Satsuma Drive Abutment Project final change order in the deduct amount of $2,957.20
 
Body
SUMMARY: The Satsuma Drive Abutment Project has been completed and a final change order is attached with the final quantities. The final change order is a deduct of $2,957.20.  Staff recommends the approval of the change order.
 
BUDGET ACCOUNT:  110-43100-930-006
 
Recommended Action
NECESSARY COUNCIL ACTION:
Approve the change order with Hopper Excavating, LLC.