File #: 26-0011    Version: 1 Name: Peavine Road Force Main Addition Change Order 1
Type: Contract Status: Consent Agenda
File created: 12/29/2025 In control: City Council
On agenda: 1/13/2026 Final action: 1/13/2026
Title: Approval of Peavine Road Force Main Addition Change Order #1
Sponsors: Engineering Department, Tim Begley
Attachments: 1. 3671-20_Change Order 1 Peavine Road Force Main Addition.pdf
Related files: 25-0256

Title

Approval of Peavine Road Force Main Addition Change Order #1

 

Body

SUMMARY: Due to field adjustments because of other utilities, the amount for contract item “6-inch force main in gravel or parking lot” has been exceeded and two other items in the contract are being reduced. This change order reduces the total contract amount by $1,101. Staff recommends the approval of the change order.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the attached change order 1.