Approval of contract amendment regarding Fourth Street & West Avenue intersection
Body
SUMMARY: The City currently has a contract with Gresham Smith Partners for the design of the traffic signal for the Fourth Street & West Avenue intersection.
The contract currently reads for each task:
NEPA Phase (Includes Survey and Planning) $29,000
ROW Plans Phase $38,000
Construction Plans Phase $29,000
Bid Documents and Specifications $7,500
There is currently an amount left over in the NEPA phase that needs to be transferred to the Construction Plans Phase in order to be reimbursed through State Transportation Improvement Funds. The proposed schedule of values is as follows:
NEPA Phase (Includes Survey and Planning) $17,304
ROW Plans Phase $38,000
Construction Plans Phase $40,696
Bid Documents and Specifications $7,500
No additional funding is requested.
BUDGET ACCOUNT: 311-43100-931-003
Recommended Action
NECESSARY COUNCIL ACTION: Approve amendment