File #: 26-0156    Version: Name: Catoosa Area Water Lines Project Close Out Change Order
Type: Contract Status: Consent Agenda
File created: 4/1/2026 In control: City Council
On agenda: 4/14/2026 Final action:
Title: Approval of Catoosa Area Water Lines Project Close Out Change Order
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Final Balancing Change Order.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsPlayback
No records to display.

Title

Approval of Catoosa Area Water Lines Project Close Out Change Order

 

Body

SUMMARY: The close out change order for the Catoosa Area Waterline project is recommended with a deductive amount of $212,940.87 with no additional days. This change order zeros out all unused quantities.

 

Staff recommends the approval of the change order.

 

BUDGET ACCOUNT:450-52140-934-009

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the attached change order.