File #: 24-0344    Version: 1 Name: Change Order 2 Downtown Sidewalk project
Type: Contract Status: Consent Agenda
File created: 9/26/2024 In control: City Council
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Approval of Change Order 2 - Downtown Sidewalk project/TAP Grant PIN 126662.00
Sponsors: Engineering Department, Tim Begley
Attachments: 1. 2024-09-26 Change Order 02 (PIN 126662.00).pdf

Title

Approval of Change Order 2 - Downtown Sidewalk project/TAP Grant PIN 126662.00

 

Body

Change order 2 for the Downtown Sidewalk project has been submitted. This change order adds 28 days to the contract time and adds an additional cost of $79,123.40 to the project. All items are unit price items and may not reach the estimated total cost.

 

This change order includes the following:

                     Conduit and pull boxes between the three traffic signals in the project for a future fiber interconnection.

                     150 linear feet of barrier rail to expand the construction zone.

                     Barrier rail reflectors required by TDOT but not originally included in the contract.

                     Unclassified excavation which is required because no gravel aggregate was found under the existing sidewalk.

This change order covers all of the foreseeable changes to the project.

 

Staff recommends the approval of the change order.

 

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve, contingent of TDOT’s approval, change order number 2 for the Downtown Sidewalk project.