File #: 23-0153    Version: 1 Name: High Mast Pole & Light Project Change Order
Type: Contract Status: Passed
File created: 5/2/2023 In control: City Council
On agenda: 6/13/2023 Final action: 6/13/2023
Title: Approval of High Mast Pole & Light Project Change Order
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Change_Order_2_Final_5-2-23.pdf
Related files: 22-0393

Title

Approval of High Mast Pole & Light Project Change Order

 

Body

SUMMARY: A final closeout change order 2 is attached for the High Mast Pole & Light at Exit 322- Interstate 40 project. The change order adds 75 days to the project, no monies and relieves the contractor of liquidated damages. The delay in the installation of the second pole was caused by material deliveries, weather conditions dealing with a crane and crane scheduling.

 

The Director of Engineering recommends the approval of the approval of the change order.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the change order No. 2 -Final as presented.