File #: 14-0350    Version: Name: Little Obed Sewer Pump Station
Type: Ordinance Status: Passed
File created: 8/12/2014 In control: City Council
On agenda: 9/9/2014 Final action: 10/14/2014
Title: Ordinance amending the FY14-15 budget for the Little Obed Sewer Pump Station Upgrade
Sponsors: Waste Water Treatment Plant
Attachments: 1. Little Obed Pump Station budget amendment
Title
Ordinance amending the FY14-15 budget for the Little Obed Sewer Pump Station Upgrade
 
Body
SUMMARY:
At the August 20th meeting, the award was made on the Little Obed Sewer Pump Station upgrade in the amount of $492,500.  With engineering, administration, and other costs, a budget amendment is required to cover the costs over the $500,000 CDBG grant.
BUDGET ACCOUNT:  413-52390-930-012
 
Recommended Action
NECESSARY COUNCIL ACTION:  Pass the budget amendment on second reading.