SUMMARY: Gresham Smith is providing a resident Project Representative for the inspection of the utility installation on Phase 3 of the Northwest Connector. The utility installation has and is taking longer than expected and the attached amendment is for 4 additional months of inspection.

 

BUDGET ACCOUNT: 413-52390-934-002

 

 

Recommended Action