Approval of Ironwood Construction Change Order-Industrial Boulevard project
Body
SUMMARY: A final closeout change order is attached which adds $18,702.10 and 245 days to the contract. The additional time is due to additional work, supply chain issues throughout the project, and the delays in boring under Highway 127 due to equipment breakdowns and delays in receiving replacement parts. The additional money is required because of additional work that was not anticipated and as-built quantities, all of which are unit price items contained in the original bid.
BUDGET ACCOUNT: 413-52390-930-003
Recommended Action
NECESSARY COUNCIL ACTION: Approve change order