File #: 18-0424    Version: 1 Name: Interchange Site Development Change Order 2
Type: Contract Status: Passed
File created: 10/31/2018 In control: City Council
On agenda: 11/13/2018 Final action: 11/13/2018
Title: Approval of Change Order #2 Interchange Business Park/Site Development for contract extension
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Change order 2.pdf

Title

Approval of Change Order #2 Interchange Business Park/Site Development for contract extension

 

Body

SUMMARY: The Contractor (Robert Clear Coal Corp.) is requesting a 14-day time extension to his contract due to the above normal rainfall encountered this year. A copy of the Change Order is attached. TNECD has approved the change order and Staff recommends the approval of the change order. 

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve change order #2