File #: 16-0015    Version: 1 Name: Discussion on light pole replacement at Warner Complex
Type: Report Status: Passed
File created: 12/18/2015 In control: Work Session
On agenda: 1/7/2016 Final action: 1/7/2016
Title: Discussion on light pole replacement at Warner Complex
Sponsors: Engineering Department, Tim Begley
Related files: 15-0347, 16-0093

Title

Discussion on light pole replacement at Warner Complex

 

Body

SUMMARY: City staff has provided a survey to VEC showing the location of all the existing electrical lighting equipment at the Warner complex and VEC has gathered existing information needed for the pricing of the lighting upgrade project.

A cost estimate and schedule will be provided at the meeting.

VEC representatives have said that new typical field lighting systems usually cost about $90,000 per field and if existing conduits can be utilized, the project could be much cheaper.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: