File #: 25-0458    Version: 1 Name: Livingston Road closure
Type: Resolution Status: Consent Agenda
File created: 11/24/2025 In control: City Council
On agenda: 12/9/2025 Final action:
Title: Approval to extend the Livingston Road closure

Title

Approval to extend the Livingston Road closure

 

Body

SUMMARY: The City Council approved the closure of Livingston Road with the new road scheduled to open in mid-January. Due to several issues that delayed the road work, the binder course of asphalt will not be installed until the asphalt plants reopen in the spring.

 

First, when the roller was compacting the subgrade, the water line began leaking. This occurred twice, and on the third occurrence City crews replaced a section of the water line. In addition, the City and the Architect worked with VEC to relocate the power poles. The new location required approval from the church, and this coordination took a considerable amount of time, further delaying construction.

 

The City is now requesting that curb and gutter be installed on the north side of Livingston Road from Main Street to the church’s new driveway. The funding for this change must be approved by the Sports Authority.

 

Approval to continue the road closure is requested until the binder course of asphalt is finalized.

 

Recommended Action

NECESSARY COUNCIL ACTION: approve continuing the road closure