File #: 26-0212    Version: 1 Name: Fire Station 2 Final Change Order 2
Type: Contract Status: Regular Agenda
File created: 4/30/2026 In control: Work Session
On agenda: 5/5/2026 Final action:
Title: Discussion regarding approval of Fire Station 2 Final Change Order 2
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Change Order #2.pdf, 2. 5 Year Weathertightness Warranty.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsPlayback
No records to display.

Title

Discussion regarding approval of Fire Station 2 Final Change Order 2

 

Body

SUMMARY: Change order 2 is recommended as the close out change order for the Fire Station 2 project. The change order is a decrease in the amount of $77,096.92 which includes the remaining contingency balance, a credit of $14,740 for the front concrete apron repair, and $6,460 for the asphalt repair at the trench drain area.

 

This change order also addresses accepting a 5-year weather tightness warranty from King Construction Group in lieu of assessing 43 calendar days liquidated damages. The warranty is also attached.

 

BUDGET ACCOUNT:311-41920-920-003

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the change order contingent on the City Attorney’s review and changes on the warranty document.