File #: 15-0204    Version: 1 Name: Downtown Waterline Project Change Order
Type: Contract Status: Passed
File created: 5/7/2015 In control: City Council
On agenda: 5/12/2015 Final action: 5/12/2015
Title: Discussion and action on Downtown Waterline Project Change Order
Sponsors: Engineering Department
Attachments: 1. Contractor's Offer
Title
Discussion and action on Downtown Waterline Project Change Order
 
Body
SUMMARY: The Contractor has offered a $40,000.00 deduct to the project if he is allowed to change the depth of the waterline to have a minimum cover of 3 feet. The project was bid at depths of over 7 feet to allow for future storm sewer and minimum depths for the relocation of overhead lines.
A recommendation from the Engineer will be available at the meeting.
 
BUDGET ACCOUNT:
 
Recommended Action
NECESSARY COUNCIL ACTION: Approve change order, contingent on TDOT's approval and accordingly with the Engineer's recommendation.