Title
Airport Storage Hangar and Site Prep
Body
SUMMARY:
Bids were received on May 28, 2015 on the airport storage hangar and site prep project. The costs will be funded through a 95/5% grant from the Department of Transportation-Aeronautics Division. Despite a good turn-out at the mandatory pre-bid meeting, only one bid was received. The sole bidder was Freitag Construction Company
$673,600 Hangar
$157,140 Site Work
$ 52,700 Alt. A - Asphalt Aircraft Ramp
$ 52,050 Alt. B - Concrete Aircraft Ramp
$883,440 Hangar + Site Work + Asphalt Aircraft Ramp
$882,790 Hangar + Site Work + Concrete Aircraft Ramp
The bid is within the budgeted amount in the grant. The Engineer and State recommend approving the bid using Alt. B in the total amount of $882,790 (local match -$44,139.50).
BUDGET ACCOUNT:
Recommended Action
NECESSARY COUNCIL ACTION: Accept bid of Freitag Construction Company with Alt. B in the total amount of $882,790, pending final approval by the engineer and Aeronautics.