File #: 16-0190    Version: 1 Name: Storage Hangar Change Order 1
Type: Contract Status: Passed
File created: 4/22/2016 In control: City Council
On agenda: 5/12/2016 Final action: 5/12/2016
Title: Approval of Storage Hangar Change Order 1
Sponsors: Engineering Department, Tim Begley
Attachments: 1. Storage Hangar Change order 1

Title

Approval of Storage Hangar Change Order 1

 

Body

SUMMARY: Additional storm sewer piping has been added to the project in order to preserve the level area beside the hangar. This will also make maintenance in the area more efficient. The total cost of the change order is $8,000 with the City’s matching portion being $400.

 

BUDGET ACCOUNT:

 

Recommended Action

NECESSARY COUNCIL ACTION: Approve the attached change order with Freitag Construction contingent on TDOT’s approval.