File #: 16-0192    Version: 1 Name: Backup generator repairs
Type: Bids/Purchases Status: Filed
File created: 4/25/2016 In control: City Council
On agenda: 5/12/2016 Final action: 5/12/2016
Title: Approval of Change Order #1 with Putnam Contracting Services
Sponsors: Catoosa Department
Indexes: Funds Budgeted
Attachments: 1. Putnam Contracting proposal, 2. Putnam Contracting Services Change Order 1

Title

Approval of Change Order #1 with Putnam Contracting Services

 

Body

SUMMARY:

The backup generator at the Genesis Road booster station has not worked for quite some time.  Putnam Contracting Services, LLC was awarded the contract on the Hwy 70N pump station generator.  They have proposed replacing the automatic transfer switch on this backup generator for $7,800 as a change order to their current contract.  The two generators will be identical. Funds are available in the 70N Pump Station Generator line item.

BUDGET ACCOUNT:  450-52140-940-004

 

Recommended Action

NECESSARY COUNCIL ACTION:  Approve repair work with Putnam Contracting Services LLC in the amount of $7,800.